field personnel, and are available to participate in a preconstruction meeting with the Contractor.
The services of an experienced geotechnical/pavement engineer is recommended to assist you
during the concrete pavement construction as required. The TSMCX is available to provide
paving workshops, to respond to construction inquiries, and to locate additional resources for
construction assistance. The resident office is encouraged to contact the design office at (xxx)
xxx-xxxx and the TSMCX before paving begins and as it progresses.
w. Post-construction data transmittal. The construction office should send a copy of all QA
and QC tests results to the design office soon after testing is completed. This data is essential for
use on subsequent projects. Data transmittal during construction is also encouraged in order to
provide current statistical analysis of field data, particularly strength, according to ACI 214. This
kind of analysis can be a significant contribution to the construction process by providing
immediate feedback not only on strength performance, but also the quality of testing performed.