ETL 1110-1-163
30 Jun 96
Are the limits of clearing
f.
Operation and maintenance requirements.
and grubbing shown on
the drawings?
Y__N__N/A__
ing criteria been addressed?
Y__N__N/A__
Has disposal of cleared
and grubbed material
Do the contract documents
been addressed?
Y__N__N/A__
adequately address mon-
itoring and inspection
Have clearing and grub-
issues for the vertical
bing been addressed in the
barrier wall?
Y__N__N/A__
contract documents? See
guide specification CEGS-
Do the contract docu-
02110, "Clearing and
ments adequately address
Grubbing."
Y__N__N/A__
maintenance and repair
issues for the vertical
barrier wall?
Y__N__N/A__
d. Health and safety.
Have health and safety
issues been addressed in
the contract documents?
See guide specification
CEGS-01110, "Safety,
Health and Emer-
gency Response."
Y__N__N/A__
e.
Chemistry.
Have chemistry require-
ments been adequately
addressed in the contract
documents? See guide spe-
cification CEGS-01450,
"Contractor's Chemical
Quality Control."
Y__N__N/A__