ETL 1110-1-163
30 Jun 96
01XXX
Spill and Discharge Control Plan
Injection Trench
01XXX
Air Monitoring
B-7. Potential List of Specification Sections
01XXX
Environmental Protection
Provided below is a list of potential specifications
01XXX
Security
that should be included in the contract documents.
Not all specifications will be applicable to every
01XXX
Regulatory Requirements
project. U.S. Army Corps of Engineers guide specifi-
cations for military construction are shown when
01XXX
Decontamination and Disposal
available. If no guide specification exists, experience
from previous sites or manufacturer specifications
01XXX
Surveys for Record Drawings
should be used by the design engineer to create a
construction specification.
01XXX
Photographic Documentation
DIVISION 1 - GENERAL REQUIREMENTS
01XXX
As-Built Drawings
CEGS-01110
Safety, Health, and Emergency
01XXX
Project Record Documents
Response
01XXX
Temporary Utilities and Controls
CEGS-01300
Submittal Descriptions
01XXX
Support Facilities
CEGS-01305
Submittal Procedures
01XXX
Demobilization and Project Close
CEGS-01440
Contractor Quality Control
Out
CEGS-01450
Chemical Data Quality Control
01XXX
Operation and Maintenance
01XXX
Summary of Work
DIVISION 2 - SITE WORK
01XXX
Order of Work
CEGS-02110
Clearing and Grubbing
01XXX
Contractor's Use of Site
CEGS-02210
Grading
01XXX
Pre-construction and Pre-work
CEGS-02233
Graded-Crushed-Aggregate Base
Conference
Course
01XXX
Progress Meetings
CEGS-02234
Subbase Course
01XXX
Special Clauses
CEGS-02272
Separation/Filtration Geotextile
01XXX
Measurement and Payment
CWGS-02411
Metal Sheet Piling
01XXX
Special Project Features
CEGS-02444
Soil-Bentonite Slurry Trench for
HTRW Projects
01XXX
Warranty of Construction
CEGS-02546
Aggregate Surface Course
01XXX
Construction General
01XXX
Onsite Camera
CEGS-02671
Ground-Water Monitoring Wells
CEGS-02831
Chain Link Fence
01XXX
Dust Control
B-15