ETL 1110-1-162
30 Sep 01
Are gas vent slip couplings required at geosynthetic
penetrations?
Y__N__N/A__
Are temporary vents required during construction to allow
placement of select fill?
Y__N__N/A__
Is exposed piping for the gas collection system UV resistant?
Y__N__N/A__
Is a condensate collection system provided for the
header piping?
Y__N__N/A__
Have material properties and placement procedures
been specified for the gas collection system?
Y__N__N/A__
Is a monitoring schedule and contingency plan specified for
the collection system and monitoring probes?
Y__N__N/A__
n. Random Fill and Regraded Waste.
Has a random fill borrow source been identified?
Y__N__N/A__
Have materials and placement requirements for random fill
been specified?
Y__N__N/A__
Is a procedural method specified for placement of the initial
lifts placed on the waste material?
Y__N__N/A__
Is the waste material to be regraded?
Y__N__N/A__
Has the excavatability of the waste material been evaluated?
Y__N__N/A__
Have lift thickness, compaction, and daily cover
requirements been specified for waste regrading?
Y__N__N/A__
Have health and safety issues been addressed?
Y__N__N/A__
Have air monitoring and surface runoff control requirements
for waste regrading been specified?
Y__N__N/A__
Are compaction requirements specified for the
landfill surface?
Y__N__N/A__
C-9