ETL 1110-1-162
30 Sep 01
monitoring been defined?
Y__N__N/A__
Have existing wells been evaluated for use as
monitoring points? Do the specifications address existing
monitoring wells that will be affected by construction
(i.e., abandonment, extension, etc.)?
Y__N__N/A__
f. Final Cover Grading Requirements.
Have the regulatory requirements for grading been met?
Y__N__N/A__
g. Cover Penetrations.
Have the number of penetrations through barrier layers
been minimized?
Y__N__N/A__
Are cover penetration requirements adequately addressed?
Y__N__N/A__
h. Leachate Control.
Are leachate collection blankets required?
Y__N__N/A__
i. Cover Surface Runoff and Erosion Control Requirements.
Have the state regulations for runoff and erosion been
determined?
Y__N__N/A__
Have surface runoff and erosion control measures been
properly designed?
Y__N__N/A__
j.
Terraces, Drop Structures, and Perimeter Drainage Controls.
Have the site-specific hydrology and hydraulics been assessed to
properly design the terraces, drop structures, and perimeter
Y__N__N/A__
k . Off-site Discharge Control.
Can gravity flow be used for off-site discharge? If not,
have storage and pumping requirements been assessed?
Y__N__N/A__
C-11