ETL 1110-1-162
30 Sep 01
Do off-site discharge control measures comply with state
and local regulations?
Y__N__N/A__
Do the off-site discharge control measures require a
Federal or state permit?
Y__N__N/A__
l. Floodplain Considerations.
Does the final cover encroach into the 100-year floodplain?
Y__N__N/A__
Will construction of the cap increase river stages?
Y__N__N/A__
Is a 404 permit required for construction of the landfill cover?
Y__N__N/A__
Are flood protection or stream bank erosion control measures
required?
Y__N__N/A__
C-5. Civil Design.
Have site access routes been addressed in the contract
documents?
Y__N__N/A__
Have phasing requirements been addressed in the contract
documents?
Y__N__N/A__
Have utility requirements been specified?
Y__N__N/A__
Are decontamination pad design, operation, and disposal
requirements specified?
Y__N__N/A__
Are security fence requirements addressed in the contract
documents?
Y__N__N/A__
Have demolition and disposal been addressed in the contract
documents?
Y__N__N/A__
Are the limits of clearing and grubbing shown on the
drawings?
Y__N__N/A__
Has disposal of cleared and grubbed material been
addressed?
Y__N__N/A__
C-13