ETL 415-3-1
30 Jun 2000
7. Procedure.
a. The DD Forms 1391 will be reviewed by a designated PDT, which may be composed of the
following disciplines:
(1) Project Manager (PDT Leader)
(2) Architect
(3) Structural Engineer
(4) Mechanical Engineer
(5) Electrical Engineer
(6) Cost Engineer
(7) Geo-technical Engineer
(8) Hydraulic Engineer
(9) Environmental Engineer / Environmentalist
(10) Antiterrorism/Force Protection
(11) Information Systems
(12) Others as applicable
b. The PDT members will be responsible to ensure that each section of the DD Form 1391, as
identified in Appendixes A, B and C is properly reviewed for their specific area of expertise, and to
coordinate with Centers of Expertise (CX) for review as required. Appendix D is a checklist to
verify more specific information for the project site and building facilities, if applicable.
c. Review comments should be concise, directive statements and not questions. Questionable
areas will be resolved within the PDT, or with the installation DPW and/or MACOM.
d. The PM will coordinate with the installation DPW and the MACOM to arrange for any
necessary site visits. The geographic District will be invited to attend, if required.
4