HAZARDOUS WASTE LANDFILL COVER DESIGN CHECKLIST
C-1. General. The purpose of this checklist is to prompt the designer or reviewer to consider all
aspects of design. The checklist covers all major areas of design. However, the designer or reviewer
must refer to the narrative and other references for detailed design criteria.
C-2. Pre-design Investigations.
a. Field Surveys and Record Searches.
Have existing documents (Remedial Investigation,
Feasibility Study, etc.) been reviewed?
Y__N__N/A__
Have recent and historical aerial photographs or mapping
been obtained?
Y__N__N/A__
Have design or as-built drawings of the site been obtained?
Y__N__N/A__
Has current topographic mapping of the site, preferably
CADD generated with 1-ft (300-mm) contour intervals,
been obtained?
Y__N__N/A__
Does topographic mapping identify all surface features
(e.g., fences, trees, buildings, etc.)?
Y__N__N/A__
Have existing monitoring wells, piezometers, etc., been
elevations been determined?
Y__N__N/A__
Has horizontal and vertical control been established and
documented?
Y__N__N/A__
Y__N__N/A__
Have utilities been researched, identified, located,
and mapped?
Y__N__N/A__
Have boundary surveys been conducted for both the
project site and impacted adjoining properties?
Y__N__N/A__
C-1