ETL 1110-1-158
28 Feb 95
APPENDIX B
SCOPE OF WORK (SOW) OUTLINE FOR A SOLIDIFICATION/STABILIZATION
TREATABILITY STUDY
NOTE: USING THIS APPENDIX. This outline is supplemented by text
describing the typical requirements for each outline topic. This
explanatory text is separated from the outline contents by rows
of asterisks. This text is for the benefit of the personnel
determining scoping requirements.
1.
Project Overview and Objectives.
1.1.
Site Background.
*****************************************************************
This section should describe past uses and disposal practices at
the site and how these activities have led to the existing
have contributed to the contamination when describing site usage.
*****************************************************************
1.2.
Existing Site Conditions.
*****************************************************************
Provide a description of all pertinent (hydrologic, geologic,
etc.) site conditions. Discuss the areas of the site which are
contaminated including the levels and ranges of contamination
found during previous investigations. Also note the estimated
quantity of contaminated material. All pertinent soil borings,
geotechnical test results and chemical test results should be
included in the appendices. Indicate the detail to which the
site has been characterized and note any obvious data gaps that
exist.
*****************************************************************
1.3.
References.
*****************************************************************
Reference EPA guidance documents, previous treatability studies,
and any project documents which could be beneficial to the
Contractor. Those documents which will be provided to the
Contractor should be noted.
*****************************************************************
1.4.