Is it written to execution year? Check against SECTION 1 Fiscal Year. Check DISCOUNT RATE % !!!
AFH PROJECTS: Should compare new construction with revitalization. Has the new construction
alternative been generated use the Tri-Service Family Housing Cost Model (if not, should be)?
SECTION 12 CRITERIA FOR PROPOSED CONSTRUCTION
Check criteria referenced. Are criteria applicable, valid and up-to-date?
Are references specific?
Are criteria calculations shown?
Is Project Development Brochure (PDB) required and discussed?
SECTION 13 FURNISHINGS AND EQUIPMENT
Are OMA equipment/furnishings identified?
Identify furnishings and associated equipment requirements.
Identify appropriation used for procurement of furnishings and equipment.
Identify project and fiscal years for which they are programmed, if appropriate.
Are furnishings and equipme nt discussed (if required)?
Has user been contacted about special requirements?
Are OPA equipment items and costs identified? The OPA equipment may include IDS, range target,
information systems equipment from Section 17, etc.
SECTION 15 ENVIRONMENTAL ANALYSIS
Section should summarize environmental impacts.
Does it contain standard statements from AR 415-15?
Is appropriate environmental documentation included (Categorical exclusion, project category, etc.)?
Is it signed by the proper party (environmental rep)?
SECTION 16 EVALUATION OF FLOOD HAZARDS
Verify project is not in flood plain (100-year flood) or wetlands. If in flood plain, state reason to put the
project there and that mitigation measures will be incorporated into the project design.
Verify that siting is not in flood plain or wetlands (500-year flood plan for critical facilities, hazardous
materials, or toxic waste sites).
Is standard statement included?
SECTION 17 INFORMATION SYSTEMS SUPPORT
Make sure this section is properly prepared by the installation DOIM and fund sources are clearly identified
in the cost estimates IAW Appendix L in the AR 415-15 for the Funding of Information Systems Support
Components.
Make sure this section is properly signed and dated.
C-5